Back to all case studies

Eliminating project overruns for a mid-size construction firm

Greystone Construction was completing projects but rarely on time or on budget. The overruns were predictable but nobody had a system for preventing them.

Construction

Organizational Alignment

73%

Reduction in projects delivered over budget

4 weeks

Average reduction in project delivery time

100%

Of staff reported clearer ownership

Customer

Greystone Construction

Industry

Construction

Employees

110

Service

Organizational Alignment

Duration

90 days

Greystone Construction is a mid-size construction firm with approximately 110 employees and a strong project pipeline. Despite capable staff and consistent demand, the business had struggled for years with project overruns — the average project came in 18% over budget and two to four weeks late. Leadership had attributed this to the inherent unpredictability of construction work, but the pattern was too consistent to be explained by circumstance alone.

Challenge

Greystone Construction had a strong pipeline and a capable team, but project overruns were a persistent problem. The average project came in 18% over budget and two to four weeks late. Leadership had attributed this to the inherent unpredictability of construction work — but when Meridian began the engagement, a different picture emerged.

The overruns weren't caused by unpredictability. They were caused by unclear ownership, inconsistent project communication and a lack of structured risk identification early in the project lifecycle.

Approach

Meridian's audit focused on the project lifecycle from contract signing through final delivery, mapping decision points, communication flows and ownership transfers at each stage. The findings identified three recurring failure patterns: scope changes that weren't being formally captured and priced, subcontractor coordination that was happening informally and late and project risk that wasn't being identified until it had already become a problem.

Meridian then facilitated a series of alignment workshops with Greystone's project leadership team to redesign the project management framework. New protocols were established for scope change management, subcontractor coordination and risk identification. Ownership of each protocol was assigned to named individuals with defined accountability.

Results

In the 12 months following the engagement, the proportion of projects delivered over budget fell by 73%. Average project delivery time shortened by four weeks. In a post-engagement survey, 100% of senior staff reported having clearer ownership of their responsibilities than they had before the engagement — a result that Greystone's leadership cited as the most significant cultural shift the firm had experienced.

Keep reading

Professional Services

Rebuilding project delivery for a 200-person firm from the ground up

Manufacturing

Cutting fulfillment delays by 40% in 90 days

Logistics

Reducing operational costs by 28% without cutting staff

Buy template